CARGILL BEEF RENDER PLANT UPGRADE

The Scope of works for this project involved supplying and installing over fourteen screw conveyors ranging in size from 4 metres to 25 metres and fabricated from both mild steel and stainless steel. The installation was to be done without any interference to the normal day to day operating procedures of the existing rendering process, with the change over on a weekend so as not to interfere with normal production.

The project was completed in a very tight schedule and without any stoppages to the normal processing facility. This shows RWI’s expertise in plant and equipment installation and our ability to provide the client with an exceptional service.

(1) 25 metre stainless steel screw conveyor and galvanised platform installed on site

conveyor

(2) Screw conveyor being installed

conveyor

(3) Equipment being installed

equipment

(4) Raw material bin ready to install

raw materials bin

(5) Installing 65 ton Keith Cooker

cooker

(6) Installed Screw Conveyor

screw conveyor

(7) Setting up Presses & Associated Plant

presses

 